



|
 |
 |

UNIVERSITY OF CALIFORNIA, LOS ANGELES [www.ucla.edu]
Problem
In 1991, UCLA decided to build a state-of-the-art chiller and cogeneration
facility to provide clean, cost-effective energy for the campus. Even
though the facility would actually lower air emissions from the campus
by 34%, the permitting process was complex and highly political. UCLA
needed to:
- Design and implement a strategy to expedite
permit approval from the South Coast Air Quality Management District
(SCAQMD) for this 45 megawatt, $188 million cogeneration project.
- Achieve broad support for the project throughout
the campus and adjoining communities.
Solution
CEA worked with university and government officials to successfully negotiate
the permitting process. Specifically, CEA:
- Developed an overall project case statement
that clearly explained the purpose and benefits of this chiller/cogeneration
project to supporters and skeptics alike.
- Worked with UCLA and the facility’s
designers to propose a project to the SCAQMD that established new Best
Available Control Technology (BACT) standards for NOx emissions and
cooling tower emissions.
- Engaged the SCAQMD staff in a collaborative
review process so that their questions and information requests were
answered quickly and completely, thereby allowing for a timely review
of the permit request.
- Formed a UCLA community briefing team to meet
with and educate legislative and other governmental officials who had
expressed concerns about the project.
Results
- CEA focused all the parties involved on solving
the problem.
- The application was deemed complete prior
to a pending rule revision thereby shortening the construction schedule
and substantially reducing overall costs.
- The process became an example for addressing
issues at the University before they became problematic and developing
creative, proactive approaches that the regulatory agency could (and
did) embrace.

|

|